End Time of Schedule Hi,
I want to know the effect of schedule end time. e.g. If I set a schedule a daily report to run at 23:50 to 23:55, what happens if the report doesn't finish at 23:55?
If the report finishes at 23:58, will it affect the execution of next day?
Thanks!
kgroff- 10-31-2008
If it is set to daily, the execution will not be affected.
If it is set to every 24 hours, then the resulting execution would be every other day.
dannyp- 11-03-2008
Daily Schedule doesn't 100% work Hi,
Thanks for your clarification. I found that some of the daily scheduled reports do not execute at the pre-defined time, but some does. If I have a log file and configuration screen, can you help to take a look?
Let me know if I can post it here.
Thanks a lot!