Posted: Tue May 06, 2008 11:25 am Post subject: Custom Calendar |
|
|
In an older version of the software, there was a custom calendar feature. I do not see this in the newer version I have now. Is this feature still in the software, or is there another way to achieve this functionality?
Thanks |
|
| Back to top |
|
 |
| kgroff Site Admin
 | | Joined: 27 Jan 2005 | | Posts: 694 | |
|
Posted: Tue May 06, 2008 1:09 pm Post subject: |
|
|
| The custom calendar is not included in any version beyond 7.0.0 (I think). |
|
| Back to top |
|
 |
| clayk
| | Joined: 06 May 2008 | | Posts: 5 | |
|
Posted: Tue May 06, 2008 1:15 pm Post subject: |
|
|
| I'm not sure how great of a grasp I have on this scheduling concept. I want to schedule a report to run only on the first day of the month. How would I go about that? |
|
| Back to top |
|
 |
| Timo Langer
| | Joined: 10 Jan 2008 | | Posts: 6 | |
|
Posted: Wed May 07, 2008 3:53 am Post subject: |
|
|
Hi,
Schedule
Export Interval: Specific Day of Month
Value: First Day
Export Days: All Days
Timo |
|
| Back to top |
|
 |
| clayk
| | Joined: 06 May 2008 | | Posts: 5 | |
|
Posted: Thu Mar 12, 2009 6:36 am Post subject: |
|
|
| If I wanted to schedule a report to run on a specific date every other month, how would I go about that? |
|